Aviator

Project Overview

Powerlines

The substation, along with new transmission infrastructure is needed to accommodate load growth and to maintain reliable electric service in the area. Rapid growth in electrical demand, particularly in the commercial/high-tech sector in Loudoun County has resulted in the need to build a new transmission line and substation. This project will improve electric reliability for all customers in the region.

For this project, we will build a new substation south of Dulles Airport near Route 50 in Loudoun County. This substation will support the construction of a new data center. In addition, we will build transmission lines to bring electricity to both the substation and data center.

The project will include the installation of new steel monopoles.

Benefits

  • Provide long-term reliability and durability without excessive maintenance
  • Deliver operational system flexibility to meet future needs
  • Comply with mandatory standards to ensure safety and reliability

Documents

Legal

SCC Applications

The Virginia State Corporation Commission (SCC) has regulatory authority over all energy providers in Virginia. Among other responsibilities, the SCC validates the need for a proposed line and approves the route and structures. In reviewing a proposed project, the SCC must consider whether potential impacts on scenic assets, historic districts and the environment have been reasonably minimized.

On 2/2/22, Dominion Energy filed its application with the SCC. The SCC issued its Final Order approving the project on 11/28/22. Documents related to the case are available to the public on the SCC Docket of the SCC website or search by Case No. PUR-2022-00012 in the " Search Cases " section. In addition, interested parties may visit the SCC Case Comments Page where individual mailboxes are available for each case accepting public comments.

Application Documents 2022

Meetings

Virtual Open House - Live Via WebEx

January 6, 2022, 5–6 p.m.

Timeline

2024

December 2024
Construction expected to end

2023

August 2023
Construction begins
February 2023
Soil borings

2022

November 28, 2022
The SCC issued its Final Order for Dominion Energy to proceed with this project.
February 2022
Project filed with the SCC
January 6, 2022
Virtual community meeting planned

2021

August 2021 - January 2022
Outreach to the community